Removal and installation of the regulator of tension
Details of installation of the regulator of tension
|
- Details of installation of the regulator of tension are shown on an illustration. To which all references which are found in the text belong.
- Remove the generator (see the Section Removal and installation of the generator).
- Turn out screws (1), release clamps (3) and uncover generating assembly (2).
- Turn out fixing screws (4) and remove the regulator of tension (5), having pulled it aside.
- Installation is made upside-down, - track correctness of connection of an element of grounding (6).
|
|
|